2020 PROJECTS

Lawrence Avenue & Carlton Street Road Reconstruction
The City of Zeeland will be reconstructing Lawrence Avenue (from the dead end to Lee Street) and Carlton Street (from Main Avenue to Washington) in 2020. Improvements include:

  • Street reconstruction
  • Replace storm sewer, water main & sanitary sewer
  • Sidewalk construction
  • Historic-style street lighting
  • Side pathway on Washington Avenue

Schedule

  • Bid Opening - January 30, 2020
  • 2nd Public Meeting - March, 2020
  • Construction - April - September (approximately 2 months per street)

Click here to view a presentation on both of these projects.


2019 PROJECTS

Washington Avenue Reconstruction Project & Roundabout


Improvements are being made all around the City. If you have questions, comments or concerns about any project in the City, please do not hesitate to contact us at 616-772-0870 or by email. We are here to serve.

  1. City Services & Infrastructure


    Physical Address
    21 S Elm Street
    Zeeland, MI 49464

    Phone: 616-772-0870
    Emergency: 616-772-2001


  2. View All
line1


Proposed Projects & Improvements


  • Downtown Snowmelt
    The City of Zeeland is currently looking at the possibility of installing snowmelt to some downtown areas. View Snowmelt Study.
  • Non-Motorized Pathway Plan
    Non-Motorized Pathway Plan-FINALIZED
  • Transportation Study Implementation Matrix
    The City of Zeeland recently engaged the services of a professional transportation engineer to evaluate a number of transportation issues within the City of Zeeland. For information on the recommended changes and implementation time frame please click here.