Beginning June of 2023, the City of Zeeland will be installing snowmelt throughout the downtown corridor of Main Avenue from Maple to State Street. The first phase of this two-year project will begin on the east side, from Maple to Centennial, possibly as far west as Church Street by the end of the year. 

Main Avenue Project Update-

November 17, 2023

Current Status

CENTENNIAL to MAPLE (including Centennial & Main Intersection)

  • Final restoration

CHURCH to CENTENNIAL

  • Conduit installation
  • Brick paver installation
  • Electrical installation
  • Sidewalk grading and installation
  • Final course of asphalt

Looking Forward

CENTENNIAL to MAPLE (including Centennial & Main Intersection)

  • Final restoration

CHURCH to CENTENNIAL

  • Sidewalk installation (north side of street)
  • Light pole and bollard installation
  • Brick paver installation (north side of street)
  • Landscaping

Traffic / Parking Updates

CENTENNIAL to MAPLE

  • Open to traffic

INTERSECTION OF CENTENNIAL AND MAPLE

  • Open to traffic

CHURCH TO CENTENNIAL

  • Open to traffic
  • Parking open on south side of the street

INTERSECTION OF CHURCH & MAIN

  • Open to traffic

All activities and schedules are subject to change.

If you would like to sign up to receive updates on the project click here.

  1. Main Ave. Downtown Streetscape & Snowmelt Project


    Physical Address
    21 South Elm Street
    Zeeland, MI 49464

    Mailing Address
    21 South Elm Street
    Zeeland, MI 49464



  2. View All