Main Avenue Downtown Streetscape and
Snowmelt Project
Beginning June of 2023, the City of Zeeland will be installing snowmelt throughout the downtown corridor of Main Avenue from Maple to State Street. The first phase of this two-year project will begin on the east side, from Maple to Centennial, possibly as far west as Church Street by the end of the year.
Main Avenue Project Update-
November 17, 2023
Current Status
CENTENNIAL to MAPLE (including Centennial & Main Intersection)
CHURCH to CENTENNIAL
- Conduit installation
- Brick paver installation
- Electrical installation
- Sidewalk grading and installation
- Final course of asphalt
Looking Forward
CENTENNIAL to MAPLE (including Centennial & Main Intersection)
CHURCH to CENTENNIAL
- Sidewalk installation (north side of street)
- Light pole and bollard installation
- Brick paver installation (north side of street)
- Landscaping
Traffic / Parking Updates
CENTENNIAL to MAPLE
INTERSECTION OF CENTENNIAL AND MAPLE
CHURCH TO CENTENNIAL
- Open to traffic
- Parking open on south side of the street
INTERSECTION OF CHURCH & MAIN
All activities and schedules are subject to change.