Beginning in January 2026, the City of Zeeland will be reconstructing Church Street from Washington Avenue to Lincoln.
Project Schedule (**Please note that all timelines are weather dependent and subject to change**)
- Central to Main will be under construction from June through August.
- Base course of asphalt – Week of September 28
- Sidewalk and snowmelt installation – Through mid-October
- Final restoration – Through October
- Main and Church intersection will be shut down to all traffic 9/23 & 9/24
- Main to Washington will be under construction October 5 to mid-November
- Washington Avenue closure – Week of October 5
- Intersections at Lincoln, Central, Centennial, Cherry & Washington will all see closures throughout the construction project.
At any time during this construction project, you can contact us at the following numbers or email at churchst@cityofzeeland.com for assistance:
City Services and Infrastructure / Project Oversight / 616.772.0870 / (Monday through Friday 8:00 AM to 5:00 PM)
24-Hour a Day Emergency Number / 616.772.2001 / (After regular business hours)