Beginning in January 2026, the City of Zeeland will be reconstructing Church Street from Washington Avenue to Lincoln.
Project Schedule (**Please note that all timelines are weather dependent and subject to change**)
- Lincoln to Central will be under construction until August.
- Sanitary Sewer Work: 7/20-8/4
- Grading, Concrete, Asphalt and Restoration: 8/5-8/21
- Lincoln Avenue Intersection open to traffic with gravel 8/7
- Central to Main will be under construction from June through August.
- Storm Sewer Work: 7/20-8/7
- Sanitary Sewer Work: 8/10-8/21
- Anticipate Central open to traffic 8/28
- Main and Church intersection will be shut down to all traffic the end of August through September.
- Main to Washington will be under construction September through October.
- Intersections at Lincoln, Central, Centennial, Cherry & Washington will all see closures throughout the construction project.
At any time during this construction project, you can contact us at the following numbers or email at churchst@cityofzeeland.com for assistance:
City Services and Infrastructure / Project Oversight / 616.772.0870 / (Monday through Friday 8:00 AM to 5:00 PM)
24-Hour a Day Emergency Number / 616.772.2001 / (After regular business hours)