Beginning in January 2026, the City of Zeeland will be reconstructing Church Street from Washington Avenue to Lincoln.

Project Schedule (**Please note that all timelines are weather dependent and subject to change**)

  • Central to Main will be under construction from June through August.
    • Base course of asphalt – Week of September 28
    • Sidewalk and snowmelt installation – Through mid-October
    • Final restoration – Through October
  • Main and Church intersection will be shut down to all traffic 9/23 & 9/24
  • Main to Washington will be under construction October 5 to mid-November
  • Washington Avenue closure – Week of October 5
  • Intersections at Lincoln, Central, Centennial, Cherry & Washington will all see closures throughout the construction project.

At any time during this construction project, you can contact us at the following numbers or email at churchst@cityofzeeland.com for assistance:

City Services and Infrastructure / Project Oversight / 616.772.0870 / (Monday through Friday 8:00 AM to 5:00 PM)

24-Hour a Day Emergency Number / 616.772.2001 / (After regular business hours)