Church Street Reconstruction Project
Beginning in January 2026, the City of Zeeland will be reconstructing Church Street from Washington Avenue to Lincoln.
Project Schedule (**Please note that all timelines are weather dependent and subject to change**)
- Lincoln to Central will be under construction until the end of June.
- Central to Main will be under construction from June through August.
- Main and Church intersection will be shut down to all traffic the month of August.
- Main to Washington will be under construction September though October.
- Intersections at Lincoln, Centennial, Cherry & Washington will all see closures throughout the construction project.
At any time during this construction project, you can contact us at the following numbers or email at churchst@cityofzeeland.com for assistance:
City Services and Infrastructure / Project Oversight / 616.772.0870 / (Monday through Friday 8:00 AM to 5:00 PM)
24-Hour a Day Emergency Number / 616.772.2001 / (After regular business hours)