Church Street Reconstruction Project


Beginning in January 2026, the City of Zeeland will be reconstructing Church Street from Washington Avenue to Lincoln.

Project Schedule (**Please note that all timelines are weather dependent and subject to change**)

  • Lincoln to Central will be under construction until August.
    • Sanitary Sewer Work: 7/20-8/4
    • Grading, Concrete, Asphalt and Restoration: 8/5-8/21
    • Lincoln Avenue Intersection open to traffic with gravel 8/7
  • Central to Main will be under construction from June through August.
    • Storm Sewer Work: 7/20-8/7
    • Sanitary Sewer Work: 8/10-8/21
  • Anticipate Central open to traffic 8/28
  • Main and Church intersection will be shut down to all traffic the end of August through September.
  • Main to Washington will be under construction September through October.
  • Intersections at Lincoln, Central, Centennial, Cherry & Washington will all see closures throughout the construction project.

At any time during this construction project, you can contact us at the following numbers or email at churchst@cityofzeeland.com for assistance:

City Services and Infrastructure / Project Oversight / 616.772.0870 / (Monday through Friday 8:00 AM to 5:00 PM)

24-Hour a Day Emergency Number / 616.772.2001 / (After regular business hours)